How do I roll back a progress information request I made accidentally using Collaborate – Request Progress Information?

You May Have Been Automatically Redirected to This Page, Which Has a New Address (URL). Please Update Your Bookmarks / Favorites Accordingly.

Resolution

Complete the following steps:

1. Open the project in which you made the request

2. Click View - Resource Usage

3. Right-click on any column header and click Insert Column from the shortcut menu

4. Select the TeamStatus Pending field and click the OK button

5. For each assignment (task), select the No value in the TeamStatus Pending field

6. Use the fill handle to fill down the No values to speed up the entry process

7. Save and publish the project